![]() |
![]() Economical Details for Bridges page 1 Cross Frame Connections: There are many ways to provide this rigid connection. Figure 2, 3 and 4 show three common methods along with their associated cost (courtesy of Duane K. Miller, The Lincoln Electric Company; and AISI). These are among the most simple, economical connections. Any details that are more complicated add cost but no additional structural value. The most cost effective means of providing the required rigidity is by fillet welding the stiffener to the flanges (Fig. 2). This creates a Category C fatigue detail at the flange subject to tension stress or stress reversals. Some engineers have a reluctance to use this detail because it does weld to the tension flange. However, research conducted in the development of the fatigue categories found that welding to the tension flange did not create any problems under the Category C stress ranges. In many cases, designs that satisfy strength and deflection criteria, result in stress ranges that also satisfy Category C. A Category B detail should not automatically be used for attaching a connection stiffener to the tension flange.
For example, in bridges carrying a Case II load frequency, and designed to satisfy strength criteria, the Category C stress range will generally not be exceeded. Likewise, for Case I load frequency, in structures designed for overload or permit vehicles, or having simple spans, Category C stress ranges will generally not be exceeded. Another common design practice is to use HS25 live loads for strength criteria, but to use HS20 live loads for fatigue analysis. Again, this will generally result in designs for which Category C stress ranges are satisfied. In all these cases, a simple welded detail is most cost effective. At those points where these stress ranges are not satisfied, two options exist. The first is to use a Category B detail. This can be done by providing a pad assembly bolted to the flange and welded to the stiffener (Fig. 3). A fully bolted connection angle (Fig. 4) could also be used, although it costs $18-20 more per connection than the welded and bolted connection. A second alternative is to reduce the computed stress range by increasing the section properties in specific locations, thus allowing the use of Category C fillet weld at all points along the girder length. A comparison of the cost to upgrade the detail versus upgrading the section indicates that it is generally more economical to use a limited number of Category B details than to increase the section. Conclusions:
Economics of Girder Spacing:
Both fabrication and erection, however, are dependent on the number of pieces to be handled in the shop and in the field. Generally speaking, anything that reduces the number of pieces also reduces the overall cost. Wider girder spacing is not of the major factors in reducing the pieces to handle, ship, erect, paint, inspect and maintain. The following information was developed using the Bethlehem plate girder optimization program. This unique program optimizes girder designs on the basis of fabrication cost, not girder weight. It considers material costs as well as the basic fabrication costs of stiffener attachment, flange and web splices, web to flange welds, shear connectors, and cleaning and painting. The program was used to compare the relative costs of 9'-8" and 12'-6" girder spacing for the sample bridges. Table 1 shows both the relative and actual cost differentials using a base price of $0.65/lb. For the fabricated girders. Girder Cost Comparison:
In addition to the obvious savings in main materials, there are other less obvious economics also. By eliminating one row of girders, we have also eliminated a row of diaphragms, 2 lines of tension flange connections, and a line of bearings. We have, however, added some cost to the slab due to thickness increase and to the deck forming. Table 2 shows the magnitude of savings available using wider girder spacings. Superstructure Cost Comparison:
Overall Conclusions:
More Information: For more information on optimizing girder design, call one of our engineers in Construction Marketing:
Economical Details for Bridges page 1 Preliminary Bridge Girder Comparisons Span Selection for Steel Bridges Economical Details for Bridges: Cross Frames and Cross Frame Connections Economical Plate Selection for Bridges Bridges Home E-mail comments to: [email protected]
|